Equipment Erection Executed Work


We have till date executed more than 15,000MT of equipment Erection jobs involving static and rotary equipments. Some of the equipments in alloy steel materials required extensive modifications prior to erections. At most of our project sites, inspection had been stringent and critically overseen by agencies like EIL, UHDE, KPG, H&G, BV, Lloyds/IBR Authorities and a host of others.

 



Some of the important projects where equipment erections were carried out recently are :

AVI – Oil India (P) Ltd. 300MT including imported equipment.
Gas Authority India Ltd. 380MT involving extensive modification.
Indian Oil Corpt. Ltd. , GR 1250MT
Bharat Starch Inds. Ltd., 1400MT.

 

We  have all the relevant tools and tackles including heavy lifting cranes to execute such operation smoothly and timely. 


List of work Executed

Description of work Client Name & Location Consultant Value in US$ (million) Year
Piping, Equipment erection & Structural steel of EPCC - 6A & 6B Residue Upgradation and MS/HSD Quality Improvement Project. Indian Oiltanking Limited Plot No. 15, MTNL Ext. Bldg., CEAT Tyre Road, Nr. Nahur railway station, Bhandup (W), Mumbai 400078 Toyo Engineers India Ltd., - Mumbai 2.33 Dec. 2009
EPC work to carry out civil, mechanical, electrical & composite works for Phase II Esterification Plant, Piyala village. AVI-Oil India (P) Ltd. (Joint Venture of IOCL, Balmer Lawrie & Nyco France.) C/o. IOCL 607, Surya Kiran Bldg, 19, K.G. Marg, New Delhi - 001. Petchem (E) Consultant – Chennai 2.5 Jan. 2004
Composite Works for debottlenecking of LLDPE, Plant at UPPC, Pata Piping work, piping size 4" to 24" Gas line approx. 10KM M/s. GAIL (India) Ltd., U.P. Petrochemical Complex, P.O. Pata, DT. Ayraiya U. P. – 206241 Engineers India Ltd., 0.9 April 2004
01No. Cone Roof Tank Sand Pad Foundation, Fabrication, Installation & calibration IOCL-Gaigaon Depot, Akola. .Indian Oil Corporation Ltd 0.7 2002
Laying of additional heavy cut line, piping work 2" to 12" (appx.6KM) & installation of pump in KRU Plant at Hazira. Oil & Natural Gas Corpt. Ltd., P.O. ONGC Nagar, Surat - 394 518. Gujarat Oil & Natural Gas Corpt. Ltd., 0.2 July. 2002
Piping work 1" to 16" (Appx. 20KM) & mechanical equipment erection at Lote Parashuram VINATI ORGANICS LTD. - Shiv Ashish, 2nd Floor, Andheri- Kurla Road, Sakinaka, Mumbai - Dalal Consultant Pvt. Ltd., - Mumbai 0.4 April 2002
EPC job for relocation of ONGC Koyali Crude Terminal at Gujarat Refinery of IOCL, Gas & piping work 2" to 16" (Appx. 5KM) Indian Oil Corporation Ltd., Gujarat Refinery, P.O. Jawaharnagar, Dist.Vadodara ,Gujarat - 391 320. .Indian Oil Corporation Ltd 0.9 May 2001
Civil works including erection of mechanical equipment and Piping for construction of proposed Retail Outlets - LSTK VIII of IOCL in Maharashtra and Gujarat MECON LTD., 3rd Floor, Tower No. 7, Vashi Railway Station Complex, Vashi, Navi Mumbai - 400 705. MECON LTD., 1.2 Nov. 2000
Mechanical Equipment erection, piping, fabrication & rubber lining for DAP Plant Indo Gulf Corpt Ltd. Unit : Birla Copper Dahej, Dist. – Bharuch Davy Power Gas Ltd., - Mumbai 0.5 March 2000
Design, Civil work, Supply Fabrication, Erection, Testing, Commissioning & Erection of mechanical equpt. & piping for LPG Bottling Plant M/s. Indian Oil Corporation Ltd. - Jharsuguda, Orissa, LPG Bottling Plant Balmer Lowri Ltd., Kolkatta 0.6 June’ 1999
Supply, Fabrication & Erection of dismantling, painting, coating, wrapping, testing & commissioning of mechanical equipment's & instruments M/s. Rubamin Pharmaceuticals Ltd., Dhabasa, Baroda Rubamin Pharmaceuticals Ltd., 0.7 May’ 1999
Equipment Erection and piping LPG gas pipelilne 1/2" to 16" (appx. 6KM) M/s. SHV Energy North West (I) Ltd. - Sarigam, Gujarat. SHV Energy North West (I) Ltd. 0.6 1997
8100 MT LPG/Propane Terminal and cross country piping work 10" & 14" (appx. 18KM) M/s. IMS Petrogas Ltd., Porbander, Gujarat IMS Petrogas Ltd., 2.3 June’ 1997
Piping & Equipment Erection, product piping work 1" to 12" (Appx. 15KM) M/s. Chemstar Organic (I) Ltd. – Baroda Dalal Consultant Pvt. Ltd., - Mumbai 1.1 Sept. 1996
Installation of Piping work 1/2" to 12" (appx. 20KM) and Equipment Erection M/s. Hindustan Organic Chemicals Ltd.,Caustic Soda Plant – Rasayani Siel India Ltd., - Delhi 0.5 Feb. 1996
Installation of Piping work 1" to 39" (appx. 50KM) and Equipment Erection. M/s. Bharat Starch Industries Ltd., Critic Acid Plant – Baroda Davy Power Gas Ltd., - Mumbai 1.3 Oct. 1995
Design, preparation of detld.drgs. Procurement of materials, fabrication, erection, testing & painting of MS storage tanks piping work 1" to 12" (appx. 10KM) & equipment erection etc M/s. Gulf Oil India Ltd., Survey No. 27/ 1, 27/10, 29 snf 30/2, Village Masat, Silvassa Khanvel Road, Dadra & Nagar Haveli Gulf Oil India Ltd., 0.7 March 1994

 

  • BASF India Ltd, Mangalore

  • Cabot India Ltd, Thane Belapur

  • Bharat Starch Inds. Ltd, Kharkari


Enquiry Now



Looking for Product Name ?